What's new

See what changed around Olive Branch. Every update keeps community observations distinct from official project information.

City Projects

Water/Sewer East Area Project 2

Official city project added

The city's Utility Infrastructure section, updated October 21, 2026, lists Water/Sewer East Area 2 as in progress with an FY2027 target. This is distinct from East Area Project 1 and both South Area projects. The project extent and exact construction-start date are not supplied.

In Progress

East Area Project 2; project extent not published

City Projects

Maywood Gas & Water Project

Official city project added

The city's Utility Infrastructure section, updated October 21, 2026, lists the Maywood Gas & Water Project as in progress with an FY2027 target. The city does not publish a project footprint on this page; no precise pin or new construction-start date is inferred.

In Progress

Maywood area; project extent not published

City Projects

Water/Sewer South Area Project 1

Agenda project added

October 20 new-business item 2 recommends accepting this project as complete and authorizing final payment. Proposed Final Change Order No. 5 would reduce the Enscor, LLC contract by $7,113 to $5,067,461.18. Completion acceptance and the Board's decision remain unverified. This is distinct from East Area Project 1 and South Area Project 2; no confirmed completion or precise map location is inferred.

Proposed / Under Review

South Area Project 1; exact project extent awaits review

City Projects

Fairhaven Raw Water Well Replacement

Agenda project added

October 20 new-business item 1 recommends accepting the replacement-well project as complete and authorizing final payment. Proposed Final Change Order No. 1 would reduce the Double S, Inc. contract by $116,500 to $1,259,600, with Final Payment No. 3 of $367,075. Completion acceptance and the Board's decision remain unverified; this is a completion-review lead, not a confirmed completion.

Proposed / Under Review

Fairhaven; exact well location awaits review

City Projects

Water/Sewer South Area Project 2

City lists utility project in progress

The city's October 21 Utility Infrastructure update lists Water/Sewer South Area 2 as in progress with an FY2027 target. The October 6 agenda also considered Change Order No. 1, adding $244,350 for a proposed contract total of $10,373,536.12; that agenda item's outcome remains unverified. The city status update establishes active progress, without specifying a construction-start date or project footprint.

Proposed / Under Review→In Progress

South Area Project 2; precise project extent not supplied in the agenda

City Projects

Airport Apron Rehabilitation, Phase 2

Official source update reviewed

Airport apron rehabilitation Phase 2 remains Under Construction. October 20, 2026 new-business item 3 considers Change Order No. 3 with Phillips Contracting Company, Inc., adding $21,339.44 for a proposed contract total of $2,916,430.44. The Board's decision on this change order has not been verified. This is distinct from the Phase 1A/1B design-grant proposal and does not establish completion.

Olive Branch Airport

City Projects

Fire Station No. 6

Official source update reviewed

Municipal fire-station project remains under construction. The city's October 19 City Facilities update lists estimated completion in FY2027. September 15 minutes approve Change Order No. 4, adding $127,968.59 and 105 calendar days, with a revised contractual completion deadline of December 2, 2026. The fiscal-year estimate and contractual deadline are different schedule references; neither establishes completion or an opening date.

Olive Branch

City Projects

Municipal Soccer Complex shared-use path

Official source update reviewed

The city's October 19 Park Developments update lists the Multi-use Trail Project at George M. Harrison Soccer Complex as under construction, with estimated completion in FY2027. This record tracks the shared-use trail, separately from the soccer-complex expansion also listed by the city.

Municipal Soccer Complex

City Projects

Lick Creek Conservatory and Recreational Area

City lists conservatory in development

The city's October 19 Park Developments update lists Lick Creek Conservatory in development with estimated completion in FY2028. This does not document a construction start. Earlier Board agenda activity concerned design and construction-engineering services for the conservatory and recreational area.

Proposed / Under Review→In Development

Olive Branch

City Projects

Water/Sewer South Area Project 2

Agenda project added

October 6 new-business item 4 considers Change Order No. 1, adding $244,350 to a W & T Contracting Corporation contract for a proposed total of $10,373,536.12. Pending verification of the Board's decision and project extent; no precise pin or new construction status is inferred from this agenda alone.

Proposed / Under Review

South Area Project 2; precise project extent not supplied in the agenda

City Projects

OLV air traffic control tower rehabilitation and modernization

Agenda project added

October 6 consent item 34 proposes submitting an Infrastructure Investment and Jobs Act competitive grant application for OLV ATCT Rehabilitation and Modernization. The agenda does not establish a grant award, project approval, or construction start.

Proposed / Under Review

Olive Branch Airport; tower project location awaits pin review

City Projects

Fire Station No. 6

Official source update reviewed

Municipal fire-station project remains under construction. September 15 minutes approve Change Order No. 4, adding $127,968.59 and 105 calendar days, with a revised contractual completion deadline of December 2, 2026. The minutes also approve additional design services; this does not establish completion.

Olive Branch

City Projects

Old Towne sanitary sewer rehabilitation

Official source update reviewed

Sanitary sewer rehabilitation remains under construction. On September 15 the Board approved Change Order No. 2, adding $15,720 and 11 calendar days, revising the contract total to $3,316,115 and the contractual completion deadline to February 1, 2027. This is a deadline, not a confirmed completion or opening date.

Old Towne Olive Branch